Latest addition to Shiziyang Bridge constructions brings main tower above 300 meters
The main tower of the under-construction Shiziyang Bridge, part of the key project of the Shiziyang Link in the Guangdong-Hong Kong-Macao Greater Bay Area, surpassed the 300-meter mark on Thursday, after a segment of the bridge was successfully hoisted.
"The current alignment precision error of the tower body is no more than 3 millimeters, and there are only 40 meters left to reach the final height of 342 meters," said Zhang Jian, deputy manager of the T8 section at CCCC Second Harbor Engineering.
The main tower of the Shiziyang Link, which crosses the Pearl River estuary, will stand roughly as tall as a 110-story building, according to Guangdong Transportation Group.
Each leg of the tower will be precisely assembled from 62 giant steel shell segments. It is scheduled to be topped out around April, and construction of the catwalk is set to begin in the second half of the year, according to Zhang Taike, the project's chief engineer.
- Macao launches Environment Day program, carbon reduction campaign
- Fuzhou's growing role as gateway for cross-Strait cooperation
- What intl youth see in China's fisheries
- China's first cruise-to-nowhere voyage sets sail from Shanghai
- China conducts maritime operation east of Taiwan island
- China activates Level-IV emergency response for geological disasters in Chongqing, Guangxi