China completes construction of first Hualong One nuclear project
![]() |
| Staff members prepare for the dome installation at No 5 unit of Fuqing Nuclear Power Plant in Fuqing, east China's Fujian province, May 25, 2017. [Photo/Xinhua] |
FUZHOU -- China successfully installed the containment dome for its first demonstration nuclear power project using Hualong One technology, a domestically developed third-generation reactor design, in East China's Fujian province on Thursday.
The hemispherical dome, weighing 340 metric tons and measuring 46.8 meters in diameter, was installed by crane on the No 5 unit of China National Nuclear Corporation (CNNC) in Fuqing City at 5:58 pm.
The installation marks the completion of construction work on the pilot project and the beginning of the assembly stage, said Yu Peigen, deputy general manager of CNNC at the site of installation.
- Experts intensify monitoring after deadly mudslide in Xizang
- Death toll rises following Jiangxi landslides
- Cross-border cooperation key to Himalayan disaster early warning
- China establishes communication channels as 261 foreign nationals remain missing
- Foreign journalists impressed by China's rapid disaster response, urge global climate action
- China assists 1,720 Nepalese border residents after mudslide hits border port