The original Topography of Shuibuya HPP
|
|
 |
River-closure of Shuibuya HPP by CGGC-Jiangnan JV on 26 Oct 2002 in which CGGC was the leading party
|
|
 |
Image of Shuibuya HPP |
|
 |
Left Toe Excavation |
|
 |
Extruded Side Wall Construction
|
|
 |
Diversion Tunnel Outlet |
|
 |
Diversion Tunnel Inlet |
|
 |
Maya Stage II Treamtent Works |
|
 |
Face concrete placement was initiated in Stage I of Shuibuya dam.
|
|
 |
Shuibuya Dam reached design El. 405 on Oct. 12 2006 across the board.
|
|
 |
All four turbo-generator units of Shuibuya HPP were installed by CGGC and the first unit passed water-filling test, started up, connected onto the power grid and operated 72 hours continuously on the first trial. The first unit was put into service on July 22 2007.
|
|
|