China has issued a notice to standardize the administration of temporary land use, consolidating existing policies to provide clearer guidance for local authorities and enterprises while strengthening farmland protection and supporting effective investment.
Issued by the Ministry of Natural Resources, the notice clarifies that temporary land refers to State-owned or collectively owned land used for construction projects or geological exploration. Such use must be ancillary and temporary, with the land capable of being restored afterward. Land intended for permanent structures or likely to suffer irreversible damage from use is not eligible for temporary use.
The document includes positive and negative lists specifying permitted and prohibited types of temporary land use to facilitate implementation.
In terms of site selection, the notice emphasizes farmland protection, requiring local authorities and enterprises to avoid occupying cultivated land whenever possible and prohibiting the use of permanent basic farmland, ecological conservation red lines and nature reserves. These requirements also apply to facilities such as beam fabrication yards and concrete mixing stations, which can have a significant impact on land.
The notice sets a maximum temporary land-use period of two years for general projects, while long-term energy, transport and water conservancy infrastructure projects may use temporary land for up to four years. Projects that have not reached the maximum permitted period may apply for an extension three months before their current approval expires. In addition, adjacent infrastructure sections of the same major project may apply to extend the use of the same plot, reducing the costs of repeated applications and land reclamation.
To streamline approval procedures, the notice specifies applicants' qualifications, required documents and approval authorities at different levels. For projects involving mixed land types, including forestland or grassland, natural resources authorities will handle applications through a unified process and coordinate with forestry departments to issue consolidated approvals, reducing the need for enterprises to make repeated visits to different departments.
The document also clarifies responsibilities for land reclamation, designating project owners as both applicants and parties responsible for restoring the land. Plots that receive formal construction approval, rural road filing or reservoir inundation approval before the temporary-use period expires are exempt from reclamation, avoiding unnecessary demolition and restoration costs.