The Inner Mongolia autonomous region has reached a major milestone in cross-regional electricity transmission, with cumulative power transmitted through its ultra-high-voltage network exceeding 1 trillion kilowatt-hours, State Grid East Inner Mongolia Electric Power Co announced.

As of early Monday, cumulative UHV power exports had reached 1.0005 trillion kWh, making Inner Mongolia the first provincial-level power-export base in China to surpass the 1 trillion kWh milestone in UHV power transmission, the company said.

One trillion kWh is enough to meet the annual household electricity needs of approximately 885 million people, equivalent to about seven years of total electricity consumption in Beijing. Generating that amount of electricity would require more than 10 Three Gorges power stations operating at full capacity for an entire year, the company noted.

The milestone marks a decade of transformation, as the company has moved from conventional power transmission to delivering green electricity, and from ensuring power gets out to ensuring it is delivered more efficiently and reliably.

The journey began a decade ago, when Inner Mongolia's first UHV project — the 1,000-kilovolt Xiliin Gol League-Shandong alternating-current transmission project — was put into operation. Over the next decade, the power company has leveraged abundant energy resources in Inner Mongolia to deliver electricity to major consumption centers in North China and East China.

The expanding transmission network has helped strengthen national energy security, support electrical supplies across the country and advance China's goals of reaching peak carbon emissions and achieving carbon neutrality, the company said.

New projects are under construction, including a UHV transmission line linking western Inner Mongolia with the Beijing-Tianjin-Hebei region, as well as one connecting Dalad Banner of Ordos, with western Inner Mongolia, said Liu Haibo, deputy director of the company's power development and planning department.

During the 15th Five-Year Plan period (2026-30), the aim is to complete six transmission corridors to deliver electricity generated in several arid regions to other parts of the country and build an interconnected UHV AC grid, Liu added.

"We will also launch full-scale construction of three UHV transmission corridors in eastern Inner Mongolia, further expanding the region's capacity to deliver electricity to other parts of the country."