New gas-fired plant enters operations in Brazil

By Zheng Xin | chinadaily.com.cn | Updated: 2021-09-17 17:14
Share
Share - WeChat
The booth of State Power Investment Corp at an industry expo in Beijing. [Photo by Da Wei/For China Daily]

Phase one of the Gas Natural Acu gas-fired power plant entered commercial operations on Friday, according to its operator State Power Investment Corporation.

With GNA I entering commercial operation, SPIC's controllable capacity in Brazil reached 2.21 Gigawatts, with a more balanced and risk-resilient portfolio in hydro, gas and wind assets.

Located at Porto do Acu in Rio de Janeiro, the GNA project includes a thermoelectric plant, a liquefied natural gas terminal, as well as a substation and a 48-kilometer transmission line.

The total planned capacity of GNA is 6.4 GW, which will be completed in four phases.

The project is jointly developed by SPIC, Siemens Energy, BP and Prumo Logistics, a Brazil-based company controlled by EIG. SPIC is the second largest shareholder with 33 percent equity.

With $1 billion of investment and 1,338 MW of installed capacity, GNA I will be able to supply energy for 6 million households.

Top
BACK TO THE TOP
English
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US
CLOSE