Rising to a tunnel's challenge

By China Daily | China Daily | Updated: 2017-06-09 07:32

When work began on the Dazhushan Tunnel, the plan was to finish it in five years. That was in 2008 - and construction crews are still digging.

Unexpected difficulties mean the 14.5-kilometer tunnel, a critical juncture on the Dali-Ruili Railway in Yunnan province, is now scheduled for completion in 2021, Xinhua News Agency reported.

The tunnel runs through six faults in the Hengduan Mountains on the Qinghai-Tibet Plateau. It would have been beyond imagination to build on the earth fractures 20 years ago, said You Hongsheng, a spokesman for No 4 Company of China Railway First Group Co, which is digging the tunnel.

Rising to a tunnel's challenge

Today's Top News

Editor's picks

Most Viewed

Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US