How major challenges were overcome

China Daily | Updated: 2016-07-02 08:25

CHALLENGE 1: Frost

About 550 kilometers of the 1,956-km railway's track is laid on permafrost, frozen soil, sediment or rock. Permafrost is defined as ground that stays frozen for at least two years. When the railway was proposed, concerns were raised that the heating systems that keep the track clear of ice and snot might melt the permafrost and affect the integrity of the track.

Solution - Dong Tianchun, an engineer at Qinghai-Tibet Railway Co who specializes in permafrost technology, said engineers solved the problem by elevating the track with pile-driven foundations sunk deep into the ground in permafrost areas. In other places, a total of 10,829 heating pipes are buried underground.

How major challenges were overcome

Today's Top News

Editor's picks

Most Viewed

Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US