Supporting projects accelerate new-type power grid construction
As the protection load test of the 110 kV Datong Line 1586 was normal and the booster station returned to normal operation mode , the agri-livestock-PV complementary photovoltaic power generation project in Hangtou town and Datong town, Jiande city, developed by Power Construction Corporation of China, was completed and went into operation on Nov 20. The 110 kV Meiling Photovoltaic Power Station was officially connected to the grid to facilitate power generation.
This is a key construction project in the clean energy supply guarantee field under Zhejiang province's "Thousand Projects, Trillion Yuan" program, with a total investment of approximately 710 million yuan ($106.44 million). Located in Datong town and Hangtou town, Jiande city, it has a construction scale of 192.4 MWp and a maximum AC-side output of 148 MW. It is also equipped with a newly built 110 kV booster station. The project adopts an agri-PV complementary model featuring power generation above the panels and crop cultivation below. The photovoltaic supports use a combined flexible and fixed design, which not only allows more modules to be installed and increases installed capacity, but also reduces the amount of concrete foundations and land occupation, improving land use efficiency per unit area.

[Photo provided to chinadaily.com.cn]
To ensure the project's smooth grid connection, the supporting 110 kV outgoing line project was invested in by State Grid Hangzhou Power Supply Company and constructed by State Grid Jiande Power Supply Company. With a total investment of approximately 43 million yuan, the line is 13.44 km long and includes 43 newly built towers, crossing the Hongtang Reservoir, Shouchang River, and multiple in-service distribution lines along the route. The project started in January, with an effective construction period of less than 10 months. The mountains are high and the forests dense, and some tower sites require nearly two hours of hiking uphill. Hard rock layers made construction difficult and slow.
A dedicated task force was set up and a daily scheduling and weekly review mechanism has been implemented, closely tracking construction progress every day and sorting out problems and optimizing plans every week. Construction personnel worked to wall charts and in shifts, ensuring high-quality and efficient progress while guaranteeing safety. Work did not stop during the Mid-Autumn Festival or National Day holidays, with about 60 construction workers deployed. Large machinery such as mobile cranes and tensioning equipment entered the site in sequence according to the construction process, steadily advancing construction progress to match the photovoltaic project's planned grid connection time.
"The outgoing line passes through complex mountainous terrain and has many crossings. The project has faced multiple challenges since construction began," said Jiang Guozhen, director of the Development and Construction Department of State Grid Jiande Power Supply Company. The project area has steep slopes and high vegetation coverage. The project team introduced drone transportation technology to transport materials such as sand and gravel, steel bars, and tower materials throughout the entire cycle, improving transportation efficiency by six to eight times. The guide ropes for stringing were also deployed by drones, eliminating the need to set up temporary cableways and minimizing disturbance to mountain forest surfaces, providing a reliable sample for green construction.
After the project is connected to the grid and put into operation, its annual power generation will be able to reach 197 million kWh, equivalent to saving 59,300 metric tons of standard coal and reducing emissions of greenhouse gases such as carbon dioxide by 162,900 tons. It will mainly benefit the service areas of Datong town and Lijia town, further meeting the growing load demand of the Hangzhou power grid, promoting regional energy structure optimization, and helping achieve the carbon peaking and carbon neutrality goals.
At present, the cumulative installed photovoltaic capacity of the Hangzhou power grid has exceeded 8 million kW, accounting for more than 50 percent of the total local power supply capacity and ranking first among provincial capital cities in eastern China. Among them, the Jiande area has achieved outstanding results in photovoltaic layout. After the Meiling Photovoltaic Power Station is put into operation, its total photovoltaic installed capacity will reach 810,000 kW, accounting for more than 85 percent of local power sources. In the past three years, its load has grown at an average annual rate of more than 50 percent, and its renewable energy penetration rate ranks among the top in the city.
In the next stage, State Grid Hangzhou will serve the construction of more photovoltaic and energy storage projects, adding green momentum to Hangzhou's efforts to build a pilot demonstration city for carbon peaking and promote high-quality economic development.