One-click load transfer boosts distribution network reliability in Quzhou
Dispatchers at State Grid Quzhou Power Supply Company used the complete outage and full transfer function of their distribution automation system to carry out a one-click load transfer across nine 110-kV feeders from Donghua Substation on Aug 31. This operation successfully adjusted grid configurations and improved the safety, stability, and reliability of the power supply.
This function, built on the D5200 system, automatically analyzes distribution network topology, retrieves substation outgoing line data, and captures key switchgear status and available transfer paths.
With remote control capabilities, it enables one‑click load transfer for outgoing substation lines. During the operation, the system automatically verifies load rates, voltage compliance, and other critical indicators to ensure accuracy and reliability.
As Quzhou's distribution network grows in scale and structural complexity, the traditional dispatching method — relying on manual calculations and step‑by‑step verification — had become time‑consuming and labor‑intensive for complex load transfers. To improve efficiency, the company actively adopted intelligent automation.
The complete outage and full transfer function encapsulates numerous manual switching steps into computerized workflows. Dispatchers need only click a button in the system; it then generates transfer plans, validates them, and executes them in batch automatically.
This represents a shift from manual sequential switching to remote automated operation, cutting switching time from hours to mere minutes. It effectively raises load transfer efficiency, reduces operational risks, and strengthens emergency response capabilities.
Looking ahead, State Grid Quzhou plans to further deepen the application of distribution automation, tap into digital potential, shorten fault handling time, accelerate power restoration, reduce customer outage hours, and continually enhance overall supply reliability.