Power Focus

First large-capacity flexible DC converter transformer delivered to Yuezhou Converter Station

chinadaily.com.cn |  Updated:2026-03-30

The first large-capacity flexible DC converter transformer for the Gansu–Zhejiang ±800 kV ultra-high voltage direct current (UHVDC) transmission project completed its final 14.6-kilometer land transport and arrived at the Yuezhou Converter Station in Shangyu district, Shaoxing on March 25.

The Gansu–Zhejiang UHVDC project is the world's first to apply flexible DC technology at both the sending and receiving ends.

Spanning six provinces over roughly 2,370 kilometers, it will deliver more than 36 billion kilowatt-hours of clean electricity to Zhejiang province annually, with new energy accounting for over 50 percent of the transmitted power.

The converter transformer delivered to Yuezhou is the world's first 750-MVA large-capacity flexible DC converter transformer.

Weighing 395 metric tons, its single-unit capacity exceeds that of conventional DC transmission transformers by more than 80 percent, making it the largest-capacity converter transformer globally and the product of fully independent research and development.

The equipment departed Changzhou, Jiangsu province, on March 6, traveling 409 kilometers via the Beijing–Hangzhou and Hangzhou–Ningbo canals.

It arrived at a temporary heavy-lift platform in Shangyu district on March 13, where a 60-meter-tall herringbone mast crane completed the lifting operation.

During the land transport phase, State Grid Zhejiang Electric Power Company assembled a specialized convoy including height-measuring vehicles, four heavy-duty tractors, and a 16-axle, 192-wheel hydraulic modular transporter.

Local public security and transportation authorities provided full escort services and adopted a phased traffic release approach to minimize disruption. The convoy overcame challenges such as a 90-degree head-to-tail swap turn and a complex slope maneuver, with four drivers coordinating precisely to ensure the equipment entered the station smoothly.

To ensure safe transport, State Grid Zhejiang worked with local departments to refine the plan through multiple rounds of optimization.

The final water-land route significantly reduced road transport distance, minimized route modifications, and lowered logistics costs. By the end of 2025, over 220 overhead obstructions had been raised or relocated, steep slopes reinforced, and five bridges strengthened with steel supports and carbon fiber sheets.

As early as Jan 9, a 490-ton counterweight model was used in a simulated transport to verify vehicle load capacity, route planning, and safety measures — laying a solid foundation for the smooth delivery of the first large-capacity converter transformer.

Construction at the Yuezhou Converter Station is now at its peak, with the foundation and firewall for the supporting converter transformer already completed. The successful installation of the first unit sets the stage for the delivery of 13 identical transformers and marks the project's entry into the peak phase of electrical installation.

Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US