Power Focus

Spring overhaul in full swing at Shaoxing Power Grid

chinadaily.com.cn |  Updated:2026-03-12

电网绍兴1.png

[Photo provided to chinadaily.com.cn]

In the early morning of March 8, over 60 maintenance workers gathered at the 500-kilovolt Chunhui Substation in Shangyu district, Shaoxing, for a safety briefing before replacing switches. Meanwhile, 116 kilometers away at the 500 kV Fengyi Substation in Shaoxing, another team of maintenance personnel was carrying out the replacement of a voltage-changing device on the Fengpai 4321 line. Operations underway at these two locations demonstrate the simultaneous advancement of two key ultra-high voltage projects, signaling the full launch of Shaoxing Power Grid's spring maintenance work for the Year of the Horse.

"As the first Grade II risk operation on the Zhejiang Power Grid after the Spring Festival, the Chunhui Substation project has made use of the planned outage window. Since March 3, we have been working to completely replace two 500 kV switches and one 220 kV switch through fully independent implementation. This task is projected to be completed within 10 days. This will eliminate such risks as guide ring loosening and switch overheating, thereby enhancing the operational reliability of the equipment," said Yang Jie, project manager of the Chunhui Substation project. 

电网绍兴2.png

[Photo provided to chinadaily.com.cn]

With the resumption of work and production across various enterprises after the Chinese New Year holiday, the load on the Shaoxing Power Grid is expected to gradually rise. 

State Grid Shaoxing Power Supply Company has planned and implemented measures, such as segmenting the 220 kV busbar to avoid simultaneous outages of the main and auxiliary buses. This approach enables power supply during maintenance while ensuring safe operations, effectively narrowing the scope of power outages and guaranteeing reliable power supply to the adjacent 220 kV hub substation. This provides solid power support for the full resumption of work and production in surrounding areas.

电网绍兴3.png

[Photo provided to chinadaily.com.cn]

For this year's spring maintenance, Shaoxing Power Supply Company plans to carry out 406 scheduled outages for main grid maintenance, covering a wide area and involving a large scale of work.

The spring maintenance work is already in full swing, laying the foundation for a strong start to the year. These efforts will further enhance the condition and operational reliability of Shaoxing Power Grid equipment, paving the way for the high-quality economic and social development of the region throughout 2026.

Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US