Power Focus

Post-holiday services help businesses resume work, injecting strong momentum into production expansion

chinadaily.com.cn |  Updated:2026-03-03

As Chinese New Year begins, a surge of activity marks the resumption of work, and key industrial projects across Hangzhou are entering a critical acceleration phase for production launch. On March 4, account managers from State Grid Hangzhou Power Supply Company proactively visited the Jiande Branch of Nongfu Spring Co to conduct a special post-holiday electricity inspection, delivering a comprehensive power service package to ensure a strong start. This initiative aims to support the company's quest for stable and high production during Chinese New Year through reliable electricity and premium services, while simultaneously ensuring the smooth commencement of Nongfu Spring's Phase 5 and Phase 6 projects.

Phase 5 of the Nongfu Spring project requires an electricity capacity of 2,500 kilovolt-amperes, while Phase 6 requires 24,600 kVA. In Phase 4, State Grid Hangzhou adopted a long-term perspective and proactive approach. By proactively aligning with local industrial planning initiatives, they completed the forward-looking design and planning for external power projects. This laid a solid foundation for future project expansion and efficient power supply, effectively meeting the core requirement of guaranteed advance planning and synchronized implementation of power facilities under the "power supply upon land acquisition" policy. 

This time, the company enhanced its one-on-one dedicated power service model by assigning personnel to manage full-process coordination. At the service site, they conducted a comprehensive check-up of existing power distribution equipment and line corridors, focusing on identifying potential hazards and providing on-site guidance for rectification and optimization. Concurrently, the service representatives gained detailed insights into the project's work resumption progress, production load plans, and the preparatory status for the commencement of Phases 5 and 6.

Moving forward, State Grid Hangzhou will continuously track the project's progress, matching the rapid pace of project construction with the acceleration of power services. It is committed to translating the policy benefits of "power supply upon land acquisition" into tangible developmental results for the enterprise, providing proactive support to ensure zero obstacles in the power supply process and facilitating the steady advancement of the Nongfu Spring project. 

The company will persistently focus on the development needs of key local industries by forming dedicated service teams. These teams will conduct regular inspections of electrical equipment, energy efficiency diagnostics, and hazard investigations, sparing no effort to ensure a safe and stable power supply while injecting new momentum into the high-quality development of local enterprises.

Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.