Power Focus

State Grid Nanjing buries overhead power lines in CBD

chinadaily.com.cn |  Updated:2026-02-06

The 10-kilovolt Qingshi Street overhead line burial project in Xuanwu district, Nanjing, was completed on Feb 4 with the removal of the final utility pole.

As an important development in Nanjing's urban renewal efforts, this project focused on enhancing the visual appeal of Xinjiekou, while simultaneously upgrading power supply reliability. 

Working under the stringent requirement of maintaining an uninterrupted power supply for the adjacent Deji Plaza throughout the entire process, State Grid Nanjing Power Supply Company achieved a "zero-perception" experience for customers during construction by utilizing secondary grid-connection technology.

南京1.png

[Photo provided to chinadaily.com.cn]

Qingshi Street is located in the core area of Xinjiekou, known as "China's Premier Business District". It serves as an important lane within the Xinjiekou area, situated close to Deji Plaza. 

Previously, the messy aerial "spider's web" of overhead wires negatively impacted the image of the Xinjiekou business district. To address this issue, State Grid Nanjing initiated the 10kV Qingshi Street overhead line burial project in late January.

The biggest challenge stemmed from the construction site's proximity to Deji Plaza, where commercial operations demand extremely high power continuity, requiring zero power interruptions. 

To solve this problem, the company conducted on-site surveys a week in advance. 

Considering the equipment characteristics of Deji Plaza's four dedicated transformers and one nearby public transformer, they developed a customized secondary grid-connection power protection plan. 

At the same time, they deployed five low-voltage generator trucks to establish a temporary power supply system, ensuring an "uninterrupted and zero-perception" power supply during construction.

南京2.png

[Photo provided to chinadaily.com.cn]

On Jan 31, after 12 consecutive hours of work, all overhead wires along Qingshi Street were removed. Throughout this period, the lights of Deji Plaza remained brightly lit without any disruption. 

Over the following days, the company proceeded to remove the local utility poles, formally completing the project late on Feb 4.

This involved the removal of seven utility poles along the street, the laying of over 200 meters of cable, and the simultaneous burial of both power and communication lines. 

This has resulted in clearer sightlines and a more orderly streetscape along the route. Furthermore, burying the cables effectively mitigates safety hazards associated with overhead lines, such as vulnerability to weather conditions, thereby improving the power supply reliability of the area.

南京3.png

[Photo provided to chinadaily.com.cn]

Since 2025, State Grid Nanjing Power Supply Company has relocated and laid 58 kilometers of cables across the city, completed the underground burial of 622 utility poles, and placed 44 kilometers of distribution network lines underground. These efforts aim to create a cleaner, more comfortable, and aesthetically pleasing living environment for the public.

Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US