Quzhou, Zhejiang: Live-line work empowers reservoir project construction
At the site of the 10-kilovolt and below power line relocation and reconstruction project for the Foxiang Reservoir in Longyou county, Quzhou, Zhejiang province, on Dec 23, the live-line work team of State Grid Quzhou Power Supply Company commenced operations when two orange insulated aerial lift trucks were put into position.
Foxiang Reservoir serves as the core water conservancy hub in northern Longyou county. The project is currently at a critical construction stage, requiring power lines along the route to be relocated and reconstructed to ensure the smooth progress of water facility expansion and supporting pump station upgrades. Since the relocated lines are directly linked to both construction power supply for the reservoir and electricity for surrounding residents' production and daily life, conventional outage-based construction would severely impact project progress and power supply stability. Therefore, live-line work has become the optimal solution to balance line relocation with power supply guarantee — completing upgrades such as tower reinforcement and equipment installation while establishing robust power support for the reservoir project.
At 9:00 am that day, at the live-line work site on the Gongping Branch of the 10 kV Xiahong Line, the site supervisor gave the command to insulate and cover lines and pole components. Clad in insulated gear, the work crew methodically began converting a suspension pole to a tension pole under load, following the procedures in the work instruction manual. This high-difficulty operation required restructuring the pole's mechanical load-bearing system while the line remained energized. The workers carefully secured insulator strings, tightened conductors, connected jumpers, measured current, and cut lines. The entire "pole upgrade" process took only two hours. Subsequently, ground personnel coordinated with the aerial lift trucks to hoist smart switches, connect leads, and install accessories.
By 1:00 pm, the operation was successfully completed, and the new equipment was put into service. "Previously, this type of renovation would have required at least eight hours of power outage. Now, lights along the entire line don't even flicker once," explained the site supervisor. Because the entire process used live-line techniques, electricity supply to surrounding enterprises and residents remained completely unaffected.
This operation not only met the power line relocation requirements for the reservoir project but also enhanced the safety and risk resilience of the lines. To date, the live-line work team of State Grid Quzhou has performed nearly 20 live-line operations for the Foxiang Reservoir project, maximizing protection for the reservoir construction and ensuring electrical supply for surrounding production and daily life.