State Grid Jiaxing powers hybrid energy storage demonstration project
The fifth impact test of the Tongjubian No 1 main transformer was successfully completed at 3:35 pm on Sept 25, marking the commissioning of the 110-kilovolt Tongjubian transmission and transformation project, built with support from State Grid Jiaxing Power Supply Company for Tongxiang Juneng Qitai Energy Storage Technology Co.
The project provides critical power support for the Hybrid Energy Storage Multi-Energy Coupling Low-Carbon Supply Demonstration Project, while also enabling the local exploration of integrated "heat + energy storage" supply solutions to accelerate the low-carbon transformation of industrial parks.
As a key supporting facility of Zhejiang province's 2023 "Pioneer" and "Leading Swallow" R&D initiative, the 110 kV Tongjubian project provides the essential physical connection for the demonstration project to access the power grid. It plays a crucial role in improving energy efficiency and advancing comprehensive energy services.
The demonstration project, with a total investment of 252.66 million yuan ($35.5 million) and covering 38 mu (about 2.53 hectares), features a hybrid energy storage system consisting of a 70-megawatt/343-megawatt-hour molten salt thermal storage unit and a 2 MW/4 MWh aqueous chemical storage system.
During off-peak hours, the system absorbs surplus grid electricity and renewable power, converting it into stored thermal energy. By day, high-pressure steam is produced through a molten salt heat exchange system, supporting combined heat and power generation, ensuring 24/7 low-pressure industrial steam supply to the Tongxiang Economic Development Zone, while also feeding power back to the grid during peak demand periods. Once operational, the project is expected to deliver 717,000 gigajoules of heat annually and 22.08 million kWh of electricity, serving as a cornerstone for the development of zero-carbon industrial parks.
To satisfy the project's urgent power needs, State Grid Jiaxing developed and optimized a tailored grid connection plan. The project adopted a T-connection to the Fengtai 1221 line, overcoming integration challenges and providing a stable main power supply. A secondary power feed was also configured from the Ling'an substation to establish a "dual-source" system, enhancing operational security. Throughout the project, the company coordinated closely with the enterprise, refined schedules, and overcame hurdles such as a short construction cycle and complex interim solutions.
"The original plan required modifications at Fengming Substation and a GIS mobile car connection. Considering the customer's pressing schedule, we ran multiple technical simulations and overcame the challenges to ensure timely commissioning," said Lin Hong, customer manager at State Grid Jiaxing.
The commissioning of the Tongjubian transmission and transformation project lays a solid foundation for the full operation of the hybrid energy storage low-carbon supply project. In the future, as storage systems and energy networks become more integrated, the project will further leverage the advantages of storing thermal energy to deliver stable, clean heat and electricity to the industrial park. It also provides valuable experience for the development of new power systems and the low-carbon transformation of industrial clusters across China.