Timeline
1958
Construction begins on the Xining-Golmud section, the first phase of the Qinghai-Xizang Railway. The project is suspended in 1961 because of economic difficulties.
1974
Construction of the Xining-Golmud section resumes, with some 60,000 workers joining the project on the plateau.
September 1979
Track laying is completed on the Xining-Golmud section, allowing provisional operations to begin.
May 1, 1984
The 814-kilometer Xining-Golmud section officially enters operation.
June 29, 2001
Construction begins on the Golmud-Lhasa section, the railway's second phase and its most technically challenging stretch, which requires solutions to permafrost and other high-altitude engineering difficulties.
July 1, 2006
The 1,142-kilometer Golmud-Lhasa section opens to traffic, marking the full operation of the Qinghai-Xizang Railway and ending Xizang's history without rail service.
Aug 16, 2014
The 251-kilometer Lhasa-Shigatse Railway, an extension of the Qinghai-Xizang Railway, opens, further improving Xizang's railway network.
June 25, 2021
The 435-kilometer Lhasa-Nyingchi Railway opens. Fuxing bullet trains make their debut in Xizang, ending the region's history without electrified railways.
SOURCE: CHINA STATE RAILWAY GROUP
Today's Top News
- China reaffirms support for multilateral trading system after G20 talks
- 'Overcapacity' debate needs a global perspective
- Latin Americans increasingly favor China in past two years
- China launches anti-dumping probe into EU p-Nitrotoluene imports
- Africa eyes industrial growth with zero tariff
- Heritage plan stresses digital tech, cooperation