Timeline
1958
Construction begins on the Xining-Golmud section, the first phase of the Qinghai-Xizang Railway. The project is suspended in 1961 because of economic difficulties.
1974
Construction of the Xining-Golmud section resumes, with some 60,000 workers joining the project on the plateau.
September 1979
Track laying is completed on the Xining-Golmud section, allowing provisional operations to begin.
May 1, 1984
The 814-kilometer Xining-Golmud section officially enters operation.
June 29, 2001
Construction begins on the Golmud-Lhasa section, the railway's second phase and its most technically challenging stretch, which requires solutions to permafrost and other high-altitude engineering difficulties.
July 1, 2006
The 1,142-kilometer Golmud-Lhasa section opens to traffic, marking the full operation of the Qinghai-Xizang Railway and ending Xizang's history without rail service.
Aug 16, 2014
The 251-kilometer Lhasa-Shigatse Railway, an extension of the Qinghai-Xizang Railway, opens, further improving Xizang's railway network.
June 25, 2021
The 435-kilometer Lhasa-Nyingchi Railway opens. Fuxing bullet trains make their debut in Xizang, ending the region's history without electrified railways.
SOURCE: CHINA STATE RAILWAY GROUP
Today's Top News
- Xi urges Chinese police to remain committed to serving people with responsibility, dedication
- China's value-added industrial output up 5.2% in August
- AI agents are rewriting how we do business today
- Xiangshan Forum looks to find the missing handshakes
- Grouping making its own decisions
- Stable ties to lift business confidence, say executives