Workers weather desert extremes to complete 'power expressway loop' in southern Xinjiang

Xinhua | Updated: 2025-07-15 10:22
Share
Share - WeChat
A drone photo shows Chen Lin (R) operating at a construction site in Minfeng county, of Hotan prefecture, Northwest China's Xinjiang Uygur autonomous region, July 13, 2025. [Photo/Xinhua]

China has finished construction of a 4,197-km extra-high voltage power transmission loop around the Tarim Basin, home to the country's largest desert, marking a major infrastructure milestone in southern Xinjiang Uygur autonomous region.

The final section of the 750-kilovolt (kV) loop, now the country's largest of its kind, was connected on Sunday, capping a 15-year project involving nine substations and nearly 10,000 steel towers, according to a subsidiary of State Grid Xinjiang Electric Power Co Ltd, which constructed the project.

The transmission line passes through extreme terrain, from the shifting sands of the desert to the high altitudes of the Kunlun Mountains.

Chen Lin arrived in March this year at the southern edge of the Taklimakan Desert, where he, side by side with over 40 colleagues, accomplished part of the transmission line construction work despite sandy gusts and scorching temperature.

1 2 3 4 5 6 7 8 9 10 11 Next   >>|
Top
BACK TO THE TOP
English
Copyright 1995 - . All rights reserved. The content (including but not limited to text, photo, multimedia information, etc) published in this site belongs to China Daily Information Co (CDIC). Without written authorization from CDIC, such content shall not be republished or used in any form. Note: Browsers with 1024*768 or higher resolution are suggested for this site.
License for publishing multimedia online 0108263

Registration Number: 130349
FOLLOW US