WASHINGTON - A plan to rebuild
a 30-mile (50-km) pipeline from Iraq's Kirkuk oil field to the Baiji refinery to
bring the Iraqi government badly needed cash is years behind schedule with no
sign it will ever be finished, an independent watchdog said on Monday.
A total of $82 million from the coalition force's Development Fund for Iraq
was allocated for the pipeline repair but it was not clear how much had actually
been spent, said the independent Office of the Special Inspector General for
Iraq Reconstruction in a report.
Kellogg, Brown and Root, a Halliburton subsidiary which was originally
supposed to build the pipeline, gave varied estimates of the actual cost of work
performed, ranging from $1.8 million in March 2004 to less than $1 million in
June 2004, the report said.
It subcontracted out much of the project to Iraq's State Company for Oil
Projects, or SCOP, a company the report called inexperienced. Three places where
the pipeline crossed canals were originally to be done by KBR but its contract
was terminated and given to Parsons Iraq Joint Venture, or PIJV.
Violence has also taken its toll on the pipeline, the report said.
"According to PIJV, four separate subcontractors have refused to complete the
remaining canal crossings (of the pipeline) because of threats and kidnappings,"
the report said.
Quality of the construction was suspect, the report said.
"The entire pipeline project lacked any significant monitoring of
construction practices," the report said. "Even though its quality assurance
program was limited, KBR identified that approximately 25 percent of SCOP's
welds were flawed."
Last, it could not be determined how much of the pipeline was completed since
inspectors could not even travel to some of the areas where the pipeline was
under construction, the report said.
But it was clear that long after the March 31, 2004, deadline for completing
the project had passed, what was supposed to be a pipeline that would bring
billions of dollars to the Iraqi government annually was instead a leaky,
polluting pipeline that carried 500,000 barrels of oil per day rather than the
800,000 the updated pipeline was designed to carry.
"Revenue potential of approximately $14.8 billion has been lost to the Iraqi
government due to the unavailability of increased capacity for moving oil," the
report said.