Home> Guide

Joining food & pharmaceutical industry's investment projects

(chinadaily.com.cn)
Updated: 2015-01-05

1. Sign a contact

2. Municipal development and reform commission

(1) Project: filing

(2) Materials: project application, proposal or feasibility report, approval

(3) Time limit: 3 working days

(4) Department: investment

3. Planning bureau

(1) Items: location permission, land use permit, building permit, project approval certificate

(2) Materials

a. Location permission: approval from development and reform commissions, project proposal

Time limit: 10 working days

Department: construction land planning department

b. Land use permit: official documents for a project approval issued by the Commission of Development & Reform, a contract on transfer of the right to use State-owned land, copies of a design institute's qualification certification;

Time limit: 10 working days

Department: construction land planning department

c. Building permit: land use, State-owned land use, plan or a general arrangement, drawings

Time limit: 20 working days;

Department: construction project planning department

d. Project approval certificate: general plan and drawing of finished construction, property survey, mapping

Time limit: 10 working days

Department: regulatory supervision department

4. Land and resources bureau

(1) Items: transfer of right to use State-owned land contract, State-owned land use certificate

(2) Transfer of State-owned land use certificate, project's location, permission

Time limit: 20 working days

Department: land department

5. Environmental protection bureau

(1) Items: environmental impact assessment

(2) Materials: project approval documents from development and reform commission and Planning Bureau, environmental impact assessment from qualified unit (one e-version, two paper), technology assessment (one e-version, four paper)

(3) Time limit: 3 working days

(4) Department: environmental assessment department

6. Housing and construction bureau

(1) Items: construction permit

(2) Materials: proof of payment of infrastructure facility fee and labor insurance, quality supervision receipt, environmental impact assessment, project construction report, building permit

(3) Time limit: 15 working days

(4) Department: marketing department

7. Industry and commerce administration

(1) Items: business license

(2) Materials: stockholder IDs and copies, name check, proof of business premises

(3) Time limit: 1 working day

(4) Department: register section

8. Quality and technical supervision bureau

(1) Items: organization code certificate, food hygiene license

(2) Materials:

a. business license

Time limit: 2 – 3 working days

Department: code office

b. food hygiene license, applicant ID or identification papers, food company name approval, food production and processing plan for place and surroundings, functional area plans, food production equipment, food production flow chart, equipment layout, technicians and managers, food safety rules, food safety standards, other evidence as required by law and regulations

c. Time limit: 40 working days

d. Department: food office

9. State tax administration and Anshun tax bureau

(1) Items: tax registration

(2) Materials: business license, organization code certificate, fixed housing proprietary certificate, land use certificate, lease contracts, Legal representative ID and copies, capital verification report or assessment report

(3) Time limit: 1 working day

(4) Department: taxes, municipal government affairs service center

10. Food and drug administration

(1) Items: drug production certificate

(2) Materials: business license, technical documents, sound and quality control system and liability system, national and industrial standards proof, health safety guarantee, industrial policy compliance proof.

(3) Department: provincial food and drug administration

11. Begin construction