CNNC boosts nuclear power output

中国核工业集团公司计划投入4千亿元资金,使核电装机容量到2020年达到4000万千瓦,这意味着未来还需要开工新建30台左右的百万千瓦级核电机组。目前,江苏田湾核电站将于2005年全部建成投运,届时核电总装机容量将达到870万千瓦。秦山二期核电站还将扩建2台65万千瓦机组,广东岭澳核电站扩建2台百万千瓦机组。同时,通过国际招标引进第三代核电技术,在浙江三门和广东阳江分别建设2台百万千瓦级机组。

 

the night piece of CNNC's Qinshan plant
the night piece of CNNC's Qinshan plant

China National Nuclear Corporation (CNNC), the nation's largest reactor builder, intends to use its own technology to build two 650-megawatt reactors and two 1,000-megawatt reactors at its Qinshan plant, which will more than double its generation capacity.

Upon completion of both projects, the installed capacity of the Qinshan nuclear power plant will be set to rise to 6,200 megawatts from the current 2,900 megawatts generated by five running reactors, a CNNC news centre official said.

Total investment for the planned expansion projects is expected to reach US$4.33 billion, based on construction costs provided by CNNC.

For the two 650-megawatt reactors, it will cost US$1,330 for each kilowatt of added capacity. The 1,000-megawatt reactors are US$30 less for each kilowatt to build because of the technology that the two gigawatt reactors will use, said company sources.

The two 650-megawatt reactors have already won final central government approval, and will be installed at the second phase project of the Qinshan plant in Zhejiang Province, which has already been operating two Chinese-designed 600-megawatt reactors, using technology known as the China Nuclear Power (CNP) 600, its own technology.

"Infrastructure for the two reactors is scheduled to commence construction next March, and the expansion project is expected to last at least five or six years," Li said.

The remaining two planned 1-gigawatt reactors will go to Fangjiashan, 650 metres away from the Qinshan phase I project, which already has one 300-megawatt reactor in operation.

The two gigawatt reactors have been designed with a new nuclear power technology, CNP 1,000, that CNNC is developing. "Both reactors will be part of the expansion of the Qinshan phase I project and have yet to win central government approval," the CNNC official said.

"We aren't sure when the approval will come - it may be in the next four or five years," said Ma Mingze, deputy-general-manager of the Qinshan Nuclear Power Co, a unit of CNNC.

A design of a prototype for the CNP 1,000 reactor may be ready by the end of the year, CNNC President Kang Rixin said.

Because of the reduced costs of the two gigawatt reactors, the power sold to electricity distributors from the CNP 1,000 plants will be 5 per cent cheaper, Kang said.

Among the five reactors in operation at the Qinshan nuclear power base, another two 700-megawatt reactors are being placed in the phase III project that uses the Candu technology developed by Atomic Energy of Canada Ltd (AECL).

China has vowed to increase the nuclear content of its power generation mix to 4 per cent by 2020 from the current 2 per cent, which can be translated into some 30 nuclear plants totalling 40 gigawatts of installed capacity.

The plant locations have been selected at Qinshan, Sanmen in Zhejiang, Yangjiang of Guangdong, Hui'an in Fujian and Haiyang in Shandong.

The aim is to spend 400 billion yuan (US$48.33 billion) on the projects within the next 15 years, said Kang. 

(China Daily)

 

Vocabulary:
 

megawatt : 兆瓦特

gigawatt : 十亿瓦特

 

 
Go to Other Sections
Story Tools
Related Stories
· CNNC boosts nuclear power output
· China aviation fuel CEO may face charges
· Oil prices rise on hurricane fear
more
 
Copyright by chinadaily.com.cn. All rights reserved

版权声明:未经中国日报网站许可,任何人不得复制本栏目内容。如需转载请与本网站联系。
None of this material may be used for any commercial or public use. Reproduction in whole or in part without permission is prohibited.