Related
22 stations along Shenyang subway Line 1 under construction
By Tu Lei (chinadaily.com.cn)
Updated: 2008-05-09 16:48 The construction of 22 stations along the Shenyang Subway Line 1 has all started, and 11 stations finished the main body structure, according to today's Xinhuanet. It is predicted that 90 percent of Line 1 construction will be finished by the year's end, including 96 percent of the tunnels, and it is expected to undergo trial operations in the middle of December 2009. Line 1 has a length of 22.2 kilometers, and the east-west extension line 1 is 5.8 kilometers. During March of this year, the main structure of the Olympic Center Station of Line 2 was completed, and Line 2 is expected to be completed in 2011. The construction of Line 1, Extension Line 1 and Line 2 started in November 2005, and the planned rail network in Shenyang is 182.5 kilometers. Shenyang City, Northeast China's Liaoning Province, is the 7th city to see subway construction in China. (For more biz stories, please visit Industries)
|